This extensive project was successfully executed using 8 of our rigging enginers in the period of 6 days, perfectly on schedule.
Impressive Spooling Operation
Responsible for overall project planning and coordination, including Job Safety Analysis and Method Statement for the entire spooling operation.
On-site NDT inspection test of boom hoist wire ropes using a magnetic NDO device. Inspection test successfully executed using our 180T and 150T spooling machines.
Simultaneous removal of existing boom hoist wire ropes (52mm, 6,800 m) using our 180T & 150T spooling machines.
Inspection and measurement of all sheaves.
Simultaneous installation of new boom hoist wire ropes (52mm, 5,800 m) using our 180T & 150T spooling machines.
Customer Wei Li
Operations NDT Test and Complete exchange of Boom Hoist wire ropes on 3000T crane